Projects / Commercial

3M Central Utility Plant Modifications – Austin, Texas

Owner: Arcadia (3M Property)
Contact Person: Brad MacDonald
Date Completed: 2022
Construction Cost: $2.2M
Project Description:

Scope of work was for a 40,000 GSF project that included the removal of a steam turbine from a combined heat and power plant and the addition of multiple gas fired boilers to serve the campus heating load. Also included in the project is the removal and replacement of a 1,500 Ton centrifugal chiller to serve the campus chilled water load.  The campus and plant automation system was studied and a design was developed to integrate all plant equipment, existing controls protocols and future building systems into a complete campus controls architecture.

Services Provided:

Jose I. Guerra, Inc. provided structural, Mechanical, electrical, plumbing, fire protection, engineering design services and complete PLC instrumentation and controls engineering design and CA services.

Slideshow (Click images below to view)