Projects / Water / Industrial
South Austin Regional Wastewater Treatment Plant – Filter Improvements Austin, Texas
Owner: City of Austin | Randy Pohren
Contact Person: AECOMĀ | John Buser, P.E.
Date Completed: November 2018
Construction Cost: $26,000,000
Project Description:
The scope of work is to provide modifications to the Filter Building that are required in order to convert to a new cloth filter system. Project is comprised of installation of the temporary filtration system, structural concrete renovations within the existing filter cells, installation of piping and valves to serve the newly installed filtration equipment, backwash pump room modifications, cleaning/coatings in the clearwell and mudwell, removal of abandoned piping, structural demolition within filter cells 7-12 and final closeout operations.
Services Provided:
Jose I. Guerra Inc. provided complete structural engineering design and construction administration services.